1.The trommel screen must be turned on before the feeding equipment; the opposite happens during downtime.
2.In the first few days of operation, the rotary drum screen fasteners should be inspected daily and tightened in time if they are loose. In the future, it can be inspected and processed regularly (weekly or half-monthly);
3.Bearing housings and gearboxes should be regularly checked for lubrication and refueled and changed in a timely manner. Under normal circumstances, add grease every two months. The filling amount should not be too much, otherwise it will easily cause the bearing to overheat. Bearings should be cleaned and inspected every year.
4.Shaking the insulation of the motor when restarting the equipment for a long period of inactivity (more than 30 days) to avoid motor burnout.